Hunts Point, Playground 52, Carmansville, MLK, and Sol Lain Playgrounds Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct public restroom buildings in various locations in the Bronx and Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: January 2018
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $9,395,000
Funding Source: Mayoral