Lincoln Terrace Park Field House Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will demolish the existing public restroom building and construct a new field house in Lincoln Terrace Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: December 2022

Construction

Start Date: September 2023
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $6,809,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Buffalo Avenue between Eastern Parkway and East New York Avenue
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024