Jesse Owens, Stockton and Stroud Playgrounds Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom buildings Jesse Owens Playground, Stockton Playground, and Stroud Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: December 2018
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $5,191,000
Funding Source: Mayoral