West Playground Public Restroom Building Construction
-
100% complete
-
100% complete
-
10% complete
This project will construct a public restroom building in West Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
January 2016
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
December 2022
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
West Playground, Brooklyn
Avenue Z between West 1st Street and West Street
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025