West Playground Public Restroom Building Construction
-
100% complete
-
100% complete
-
5% complete
This project will construct a public restroom building in West Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
January 2016
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
December 2022
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
West Playground, Brooklyn
Avenue Z between West 1st Street and West Street
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024