Bowne Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, asphalt field, seating area and swings at Bowne Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
January 2016
Completion Date:
February 2016
Procurement
Start Date: February 2016
Projected Completion Date:
October 2016
Completion
Date:
July 2017
Construction
Start Date: August 2017
Projected Completion Date:
February 2019
Completion Date: April 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bowne Playground, Queens
Union Street between Sanford Avenue and Barclay Avenue
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025