Bowne Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, asphalt field, seating area and swings at Bowne Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: January 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: October 2016
Completion Date: July 2017

Construction

Start Date: August 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $5,386,000
Funding Source: Mayoral

Location

Bowne Playground, Queens
Union Street between Sanford Avenue and Barclay Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025