Luther Gulick and Yolanda Garcia Park, Lyons Square, Saw Mill, and Ten Eyck Playgrounds Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct public restroom buildings at Yolanda Garcia Park, Lyons Square Playground, and Saw Mill Playground in the Bronx; Ten Eyck Playground in Brooklyn; and Luther Gulick Park in Manhattan, and reconstruct Saw Mill Playground with a basketball court, track and synthetic turf field, fitness and play equipment, and a spray shower.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
February 2016
Completion Date:
February 2016
Procurement
Start Date: February 2016
Projected Completion Date:
October 2016
Completion
Date:
December 2016
Construction
Start Date: February 2017
Projected Completion Date:
August 2018
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Luther Gulick Park, Manhattan
Columbia St, Delancey St & Bialystoker Pl
Community Board: 03 -
Lyons Square Playground, Bronx
Aldus St to Bruckner Blvd bet Bryant Av & Longfellow Av
Community Board: 02 -
Saw Mill Playground, Bronx
E. 139 St. bet. Brook Ave. and Willis Ave.
Community Board: 01 -
Ten Eyck Playground, Brooklyn
Scholes St bet Bushwick Av & Waterbury St
Community Board: 01 -
Yolanda GarcĂa Park, Bronx
Melrose Avenue between East 160 Street and East 159 Street
Community Board: 03
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 11/22/2024