Asser Levy Park Flagpole Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new flagpole and install a bluestone path in Asser Levy Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: October 2014
Completion Date: December 2014

Procurement

Start Date: December 2014
Projected Completion Date: September 2015
Completion Date: March 2015

Construction

Start Date: April 2015
Projected Completion Date: September 2015
Completion Date: September 2015

Understand how we build parks.

Funding

Total Funding: $67,000
Funding Sources:
  • City Council
  • Mayoral

Location

Asser Levy Park, Brooklyn
West 5th Street and Surf Avenue
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024