Marine Park Salt Marsh Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: April 2020
Completion Date: April 2021

Construction

Start Date: September 2021
Projected Completion Date: March 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Source: Mayoral

Location

Marine Park, Brooklyn
Avenue U and East 33rd Street
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024