Marine Park Salt Marsh Nature Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Salt Marsh Nature Center to provide additional office and exhibition space and ADA access outside the building, around the bluff perimeter.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
August 2019
Procurement
Start Date: August 2019
Projected Completion Date:
April 2020
Completion
Date:
April 2021
Construction
Start Date: September 2021
Projected Completion Date:
March 2023
Completion Date: March 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Marine Park, Brooklyn
Avenue U and East 33rd Street
Community Board: 15, 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024