Rapkin-Gayle Plaza - New Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

The project will construct a new open space at the DEP site at Grand Street and Lafayette Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: September 2021

Construction

Start Date: October 2021
Projected Completion Date: October 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $1,976,000
Funding Sources:
  • City Council
  • Mayoral

Location

Grand Street & Lafayette Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025