Washington's Walk Fort Four Playground Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    89% complete

This project will construct a public restroom building in Fort Four Playground at Washington's Walk.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: November 2022

Construction

Start Date: April 2023
Projected Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $3,620,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Washington's Walk, Bronx
Sedgwick Avenue, Reservoir Avenue, Webb Avenue
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024