Socrates Sculpture Park Seawall Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct a portion of the existing shoreline and upland path at Socrates Sculpture Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2022
Completion Date: December 2023

Procurement

Start Date: December 2023
Projected Completion Date: December 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Socrates Sculpture Park, Queens
Vernon Boulevard between Broadway and 31st Avenue
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024