Socrates Sculpture Park Seawall Reconstruction (Hurricane Sandy)
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct a portion of the existing shoreline and upland path at Socrates Sculpture Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2022
Completion Date:
December 2023
Procurement
Start Date: December 2023
Projected Completion Date:
December 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Socrates Sculpture Park, Queens
Vernon Boulevard between Broadway and 31st Avenue
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024