General Hart Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct General Hart Playground, including play equipment, swings, spray shower, basketball courts, planting, pavement, fencing, and benches.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: October 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $2,972,000
Funding Sources:
  • Borough President
  • City Council

Location

General Hart Playground, Queens
37th Avenue, 65th Street, 69th Street, Broadway
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project