Spuyten Duyvil Playground Spray Shower Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the spray shower at Spuyten Duyvil Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2016
Projected Completion Date:
February 2017
Completion Date:
March 2017
Procurement
Start Date: March 2017
Projected Completion Date:
December 2017
Completion
Date:
July 2018
Construction
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date: October 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- State
Location
Spuyten Duyvil Playground, Bronx
Douglas Avenue between West 235th Street, and West 236th Street.
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025