Spuyten Duyvil Playground Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the spray shower at Spuyten Duyvil Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $1,051,000
Funding Sources:
  • City Council
  • State

Location

Spuyten Duyvil Playground, Bronx
Douglas Avenue between West 235th Street, and West 236th Street.
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project