Marlboro Playground Security Lighting Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a park security lighting system in Marlboro Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2015
Projected Completion Date: September 2015
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: December 2016
Completion Date: March 2017

Understand how we build parks.

Funding

Total Funding: $89,000
Funding Source: City Council

Location

Marlboro Playground, Brooklyn
West 11th Street and Avenue W
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024