Silent Spring Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Silent Spring Playground in Kissena Corridor Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: July 2016
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: October 2017

Construction

Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $1,737,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Kissena Corridor Park, Queens
Colden Street between Juniper Avenue and Geranium Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025