Rockaway Beach Shore Front Parkway Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball courts at Rockaway Beach.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: November 2016
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: November 2018

Construction

Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $3,576,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 102nd Street and Beach 105th Street
Community Board: 14

 