Rockaway Beach Shore Front Parkway Handball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the handball courts at Rockaway Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
November 2016
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
November 2018
Construction
Start Date: March 2019
Projected Completion Date:
March 2020
Completion Date: March 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
Location
Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 102nd Street and Beach 105th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025