Jacob Javits Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, basketball court, drainage and water supply systems and surrounding landscape, and construct new adult fitness equipment at Jacob Javits Playground in Fort Tryon Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2015
Projected Completion Date:
December 2016
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
June 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Private
Location
Fort Tryon Park, Manhattan
Margaret Corbin Plaza between Cabrini Boulevard and Fort Washington Avenue
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024