Davidson Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct Davidson Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2019
Projected Completion Date:
December 2020
Completion Date:
January 2021
Procurement
Start Date: January 2021
Projected Completion Date:
October 2021
Completion
Date:
October 2022
Construction
Start Date: November 2022
Projected Completion Date:
April 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Davidson Park, Bronx
1801 Davidson Avenue between West 176th Street and West 177th Street
Community Board: 05
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024