Millbrook Playground Basketball and Handball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts at Millbrook Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: March 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: April 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,003,000
Funding Sources:
  • Borough President
  • City Council

Location

Millbrook Playground, Bronx
Bruckner Boulevard between Cypress and St. Ann's Avenues
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025