Edenwald Playground Basketball Courts and Mini Pool Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts, demolish the existing above-ground mini-pool and construct a new in-ground mini-pool at Edenwald Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
October 2016
Completion Date:
July 2020
Procurement
Start Date: July 2020
Projected Completion Date:
March 2021
Completion
Date:
August 2022
Construction
Start Date: November 2022
Projected Completion Date:
February 2024
Completion Date: June 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Edenwald Playground, Bronx
Schieffelin Avenue between East 225th and East 229th Streets
Community Board: 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025