Edenwald Playground Basketball Courts and Mini Pool Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts, demolish the existing above-ground mini-pool and construct a new in-ground mini-pool at Edenwald Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: August 2022

Construction

Start Date: November 2022
Projected Completion Date: February 2024
Completion Date: June 2024

Understand how we build parks.

Funding

Total Funding: $4,217,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Edenwald Playground, Bronx
Schieffelin Avenue between East 225th and East 229th Streets
Community Board: 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025