Co-Op City Field Irrigation System Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install an irrigation system at Co-op City Field.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Completion Date: March 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $845,000
Funding Sources:
  • City Council
  • Mayoral

Location

Co-op City Field, Bronx
Co-op City Boulevard, Bellamy Loop, Hutchinson River
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024