Riverside Park 109th Street Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing skate park with new skate elements, fencing, benches, picnic tables, and landscaping at West 109th Street in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: March 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: December 2018
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $2,865,000
Funding Sources:
  • Borough President
  • City Council

Location

Riverside Park, Manhattan
Between Henry Hudson Parkway and Riverside Drive at West 109th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024