Riverside Park West 91st-96th Streets Sidewalk Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install hexagonal asphalt pavers, benches, and granite block pavement to replace existing deteriorated paving and site furnishings, clear drainage systems, repaint the retaining wall, and plant new street trees from West 91st Street to West 96th Street in Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
October 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
October 2016
Construction
Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date: October 2017
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Riverside Park, Manhattan
Riverside Drive between West 91st Street and West 95th Street in Riverside Park, Borough of Manhattan.
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project