Riverside Park West 91st-96th Streets Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install hexagonal asphalt pavers, benches, and granite block pavement to replace existing deteriorated paving and site furnishings, clear drainage systems, repaint the retaining wall, and plant new street trees from West 91st Street to West 96th Street in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: October 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: October 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: October 2017

Understand how we build parks.

Funding

Total Funding: $747,000
Funding Sources:
  • Borough President
  • City Council

Location

Riverside Park, Manhattan
Riverside Drive between West 91st Street and West 95th Street in Riverside Park, Borough of Manhattan.
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025