Citywide Energy Efficient Lighting Installation (CNYG-2415MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will upgrade lighting fixtures to improve energy efficiency at various locations citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: November 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: November 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,262,000
Funding Source: Mayoral

Locations

  • Astoria Park, Queens
    Astoria Park South, 21 Street, Hoyt Avenue, Ditmars Boulevard, East River
    Community Board: 01
  • Chelsea Recreation Center, Manhattan
    Southside West 25 Street, 9 to 10 Avenues
    Community Board: 04
  • Clove Lakes Park, Staten Island
    Slosson Avenue, Victory Boulevard, Clove Road
    Community Board: 01
  • Constance Baker Motley Recreation Center, Manhattan
    East 54 Street between 1 Avenue and 2 Avenue
    Community Board: 06
  • Crotona Park, Bronx
    Fulton Avenue, Crotona Park North, South, East
    Community Board: 03
  • Flushing Meadows Corona Park, Queens
    (East) Van Wyck Expressway to (North) Long Island Railroad to (West) Passerelle Building
    Community Board: 03, 04, 06, 07, 08
  • Flushing Meadows Corona Park, Queens
    Grand Central Parkway, Van Wyck Expressway
    Community Board: 03, 04, 06, 07, 08
  • Forest Park, Queens
    Park Lane (to East & South) to (West) Metropolitan Avenue
    Community Board: 05, 05, 06, 09
  • Herbert Von King Park, Brooklyn
    Greene, Marcy, Lafayette, Tompkins Avenues
    Community Board: 03
  • High Rock Park, Staten Island
    Richmond Parkway & Moravian Cemetary at Rockland Avenue
    Community Board: 02
  • Highbridge Park, Manhattan
    West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
    Community Board: 10, 12
  • Kingsbridge Heights Community Center, Bronx
    Kingsbridge Terrace between Perot Street and Summit Place
    Community Board: 08
  • Kwame Ture Recreation Center, Bronx
    West 172 Street between Nelson Avenue, Jesup Street
    Community Board: 04
  • Owen F. Dolen Park, Bronx
    East Tremont, Westchester, Lane Avenues
    Community Board: 10
  • Prospect Park, Brooklyn
    450 Flatbush Avenue
    Community Board: 06, 07, 08, 09, 14
  • Randall's Island Park, Manhattan
    Little Hell Gate Inlet, Parking Lots, Perimeter Path, Triboro Bridge Ramp
    Community Board: 11
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024