Noble Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at Noble Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
June 2019
Completion
Date:
March 2021
Construction
Start Date: June 2021
Projected Completion Date:
September 2022
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Noble Playground, Bronx
East 177th Street between Noble Avenue and Bronx River Parkway
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome