Wolfe's Pond Park Playground Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Sandy-damaged playground and adjacent pathways at Wolfe's Pond Park, including new asphalt pavement, safety surfacing, fencing, benches, and curbs.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: June 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: January 2016
Completion Date: April 2017

Construction

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $915,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Wolfe's Pond Park, Staten Island
Cornelia Avenue, Chester Avenue, Raritan Bay
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024