Bayside Marina Electrical Systems Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This contract will replace electrical equipment, conduits and cable damaged by Hurricane Sandy at Bayside Marina.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2014
Projected Completion Date:
January 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
July 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date: May 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Cross Island Parkway, Queens
Cross Island Parkway and 28th Avenue
Community Board: 07, 11, 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project