Kolbert Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball courts and expand the play area to include new basketball courts, new synthetic turf field & walking track, new play equipment, and new adult fitness equipment at Kolbert Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: November 2015
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: December 2016
Completion Date: December 2016

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,851,000
Funding Source: City Council

Location

Kolbert Playground, Brooklyn
Avenue L, East 17th Street, East 18th Street
Community Board: 14

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025