McGolrick Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at McGolrick Park, including the play equipment, spray shower, pavement, fencing, benches, and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2014
Projected Completion Date:
August 2015
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
March 2017
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date: September 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Msgr. McGolrick Park, Brooklyn
Nassau Avenue between Monitor Street and Russell Street
Community Board: 01
Project Staff
Project Liaison: Davey Ives