Stroud Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Stroud Playground, including the multi-use area, landscaping, play equipment, safety surface, spray shower, seating areas, basketball court and handball court.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $4,626,000
Funding Sources:
  • City Council
  • Mayoral

Location

Stroud Playground, Brooklyn
Classon Avenue between Park Place and Sterling Place
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024