Heckscher Playground Synthetic Turf Field Construction and Sports Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new synthetic turf field with walking track and spectator bleachers, and reconstruct the basketball courts, handball courts, benches, landscaping, and lighting at Heckscher Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2014
Projected Completion Date:
April 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
January 2016
Completion
Date:
September 2015
Construction
Start Date: October 2015
Projected Completion Date:
October 2016
Completion Date: June 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Heckscher Playground, Brooklyn
Linden Street between Wilson Avenue and Central Avenue
Community Board: 04
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025