Heckscher Playground Synthetic Turf Field Construction and Sports Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new synthetic turf field with walking track and spectator bleachers, and reconstruct the basketball courts, handball courts, benches, landscaping, and lighting at Heckscher Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: April 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: January 2016
Completion Date: September 2015

Construction

Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,804,000
Funding Sources:
  • Borough President
  • City Council

Location

Heckscher Playground, Brooklyn
Linden Street between Wilson Avenue and Central Avenue
Community Board: 04

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025