Marine Park Golf Course Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pavement, curbs, and drainage at the main entrance and areas adjacent to the clubhouse within Marine Park Golf Course.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021
Completion Date: October 2022

Construction

Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $1,419,000
Funding Sources:
  • Borough President
  • City Council

Location

Marine Park, Brooklyn
2880 Flatbush Avenue
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024