Buono Beach and Alice Austen Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the landscape elements at Alice Austen Park including picket fences and paths due to damage sustained during Hurricane Sandy. The project will also include the installation of security lighting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: March 2015
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $697,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Alice Austen Park, Staten Island
Edgewater Street and Hylan Boulevard
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project