Design
Assigned & Start Date: September 2014
Projected Completion Date:
March 2015
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
June 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Alice Austen Park, Staten Island
Edgewater Street and Hylan Boulevard
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025