Nelson Avenue Waterfront Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Hurricane Sandy-damaged playground and landscape at Nelson Avenue Waterfront Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2014
Projected Completion Date: March 2015
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,846,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Seaside Wildlife Nature Park, Staten Island
Cleveland Avenue and Nelson Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project