Tribute Park Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Tribute Park due to damage from Hurricane Sandy.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: December 2019
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $2,463,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Tribute Park, Queens
Beach Channel Drive Between Beach 116th and Beach 117th Streets.
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024