Forest Park Greenhouse Palm House Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the Palm House at the Forest Park Greenhouse.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2015
Projected Completion Date:
March 2018
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
April 2020
Completion
Date:
March 2024
Construction
Start Date: September 2024
Projected Completion Date:
March 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
- Mayoral
Location
Forest Park, Queens
Woodhaven Boulevard, Myrtle Avenue, Forest Park Drive, 88th Lane
Community Board: 05, 05, 06, 09
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024