Junction and Corona Golf Playground Play Equipment Installation (QG-615M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install special needs play equipment for Fort Totten and Crocheron Park and a safety surface for Corona Golf and Junction Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: December 2014
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: March 2016

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,835,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025