Bronx Street Tree Planting FY15 - Community Boards 9-12
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 9-12 in the Bronx.
Project Timeline
Design
Assigned & Start Date: July 2014
Projected Completion Date:
August 2014
Completion Date:
August 2014
Procurement
Start Date: August 2014
Projected Completion Date:
May 2015
Completion
Date:
May 2015
Construction
Start Date: April 2015
Projected Completion Date:
April 2016
Completion Date: April 2016
Understand how we build parks.
Funding
Funding Source: Mayoral