Bronx Street Tree Planting FY15 - Community Boards 9-12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 9-12 in the Bronx.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: August 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: April 2016

Understand how we build parks.

Funding

Total Funding: $1,658,000
Funding Source: Mayoral