Brooklyn Street Tree Planting FY15 - Community Boards 5,8,9,16,17

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 5, 8, 9, 16 and 17 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: August 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $1,621,000
Funding Source: Mayoral

Location

Various locations, Brooklyn

Project Staff

Contact NYC Parks about this project