Twenty-Four SycamoresPublic Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Twenty-Four Sycamores Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: March 2016
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: November 2019
Projected Completion Date: May 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $1,643,000
Funding Source: City Council

Location

Twenty-Four Sycamores Park, Manhattan
FDR Drive, East 60th Street, East 61st Street, York Avenue
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024