Grandview Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, courts, and multi-use fields in Grandview Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: January 2017
Completion Date: January 2017

Construction

Start Date: January 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $5,090,000
Funding Sources:
  • City Council
  • Mayoral

Location

The Big Park, Staten Island
Grandview Avenue & Continental Place.
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024