Queens Street Tree Planting FY15 - Community Boards 7,8,11,12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Community Boards 7, 8, 11 and 12 in Queens.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: August 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: April 2016

Understand how we build parks.

Funding

Total Funding: $1,400,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations, Queens

Project Staff

Contact NYC Parks about this project