Manhattan Roofing Systems Reconstruction (MG-215M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roofing systems at various facilities in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2014
Projected Completion Date:
July 2014
Completion Date:
October 2014
Procurement
Start Date: October 2014
Projected Completion Date:
July 2015
Completion
Date:
November 2016
Construction
Start Date: March 2017
Projected Completion Date:
March 2019
Completion Date: March 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Annunciation Playground, Manhattan
Convent and Amsterdam Av, W 135 St
Community Board: 09 -
Asser Levy Playground, Manhattan
E. 23 St. To E. 25 St., FDR Drive
Community Board: 06
Project Staff
Project Liaison: Cristin Leoutsakos