Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-415M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roofing systems at various facilities in Brooklyn and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: November 2015

Construction

Start Date: March 2016
Projected Completion Date: March 2018
Completion Date: July 2017

Understand how we build parks.

Funding

Total Funding: $2,352,000
Funding Source: Mayoral

Locations

  • Betsy Head Park, Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
    Community Board: 16
  • Canarsie Park, Brooklyn
    Seaview Avenue between Paerdegat Basin and East 93 Street, East 102 Street and Fresh Creek Basin
    Community Board: 18
  • Clove Lakes Park, Staten Island
    Clove Road & Forest Avenue
    Community Board: 01
  • Heckscher Playground, Brooklyn
    Linden Street between Central Avenue and Wilson Avenue
    Community Board: 04
  • Jackie Robinson Playground, Brooklyn
    Sullivan Place & Franklin Avenue, Montgomery Street
    Community Board: 09
  • Sunset Park, Brooklyn
    41 Street, 44 Street, between 5 Avenue and 7 Avenue
    Community Board: 07
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project