Bronx and Queens Roofing Systems Reconstruction (CNYG-315MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofing systems at various sites in the Bronx and Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2014
Projected Completion Date: July 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2019
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,549,000
Funding Source: Mayoral

Locations

  • Bronx Park, Bronx
    Burke Ave., E. 180 St. bet. Dr. Kazamiroff Blvd., Southern Blvd. and Bronx Park E., Unionport Rd.
    Community Board: 06, 07, 11, 12
  • Corona Golf Playground, Queens
    109 Street between 46-47 Avenues
    Community Board: 04
  • Crotona Park, Bronx
    Crotona Park North to South, Fulton Av to Southern Blvd & Crotona Park East
    Community Board: 03
  • Forest Park, Queens
    (Southeast) West Main Drive to Eastern Side of Gold Course
    Community Board: 05, 05, 06, 09
  • Forest Park, Queens
    Myrtle Avenue, Union Turnpike, Park Lane South
    Community Board: 05, 05, 06, 09
  • Helen Marshall Playground, Queens
    25th Avenue & 98 Street
    Community Board: 03
  • Poppenhusen Playground, Queens
    20 Avenue between 123 Street and 124 Street
    Community Board: 07
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project