Bronx and Queens Roofing Systems Reconstruction (CNYG-315MA)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct roofing systems at various sites in the Bronx and Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2014
Projected Completion Date:
July 2014
Completion Date:
October 2015
Procurement
Start Date: October 2015
Projected Completion Date:
July 2016
Completion
Date:
January 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2019
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Bronx Park, Bronx
Burke Ave., E. 180 St. bet. Dr. Kazamiroff Blvd., Southern Blvd. and Bronx Park E., Unionport Rd.
Community Board: 06, 07, 11, 12 -
Corona Golf Playground, Queens
109 Street between 46-47 Avenues
Community Board: 04 -
Crotona Park, Bronx
Crotona Park North to South, Fulton Av to Southern Blvd & Crotona Park East
Community Board: 03 -
Forest Park, Queens
(Southeast) West Main Drive to Eastern Side of Gold Course
Community Board: 05, 05, 06, 09 -
Forest Park, Queens
Myrtle Avenue, Union Turnpike, Park Lane South
Community Board: 05, 05, 06, 09 -
Helen Marshall Playground, Queens
25th Avenue & 98 Street
Community Board: 03 -
Poppenhusen Playground, Queens
20 Avenue between 123 Street and 124 Street
Community Board: 07
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project