Flushing Meadows Corona Park Meadow Lake Northwest Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pedestrian and vehicle pathways in Flushing Meadow Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: September 2020
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021
Completion Date: September 2022

Construction

Start Date: December 2022
Projected Completion Date: December 2023
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $7,037,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Flushing Meadows Corona Park, Queens
Northwest side of Meadow Lake, east of Grand Central Parkway between Long Island Expressway and 64th Road.
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024