Cunningham Park Picnic Area Reconstruction and Performance Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the picnic area and the adjacent pathways, and construct a performance area in Cunningham Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
March 2016
Completion Date:
May 2016
Procurement
Start Date: May 2016
Projected Completion Date:
January 2017
Completion
Date:
March 2017
Construction
Start Date: June 2017
Projected Completion Date:
September 2018
Completion Date: September 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Cunningham Park, Queens
Grand Central Parkway between 193rd Street, Francis Lewis Boulevard, Hollis Hills Terrace and 210th Street.
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024