Brookville Park Picnic Area Reconstruction and Tennis Courts Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the picnic area and construct a tennis court and lighting at Brookville Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: May 2016
Completion Date: April 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $2,737,000
Funding Sources:
  • City Council
  • Mayoral

Location

Brookville Park, Queens
Brookville Boulevard, 232nd Street, 144th Avenue and 145th Avenue.
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025