Elmhurst Park Vietnam Veterans Memorial Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a memorial to Vietnam War veterans from Queens in Elmhurst Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: December 2019
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $1,958,000
Funding Sources:
  • Borough President
  • City Council

Location

Elmhurst Park, Queens
Grand Avenue between 57th Avenue and 79th Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024