Sandpiper Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Sandpiper Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: May 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $6,956,000
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 105th Street and Beach 108th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024